Another successful delivery by the Jakebe Construction team at Tyseley Depot.
Completed works include:
· CAT scan and excavation across two sections in preparation for trough installation
· Section 1: 13m trough route
· Section 2: 40m trough route
· Troughs loaded out to site and installed to line and level
· Ducting installed within troughs and lids fitted
· Backfilled and surrounding ground reinstated
· Site left clean and tidy on completion
Excellent work on site by Dave and Andy, delivering the works safely, efficiently, and to a high standard.
Great work Lads!!